Q51. You are the Scrum Master for four Scrum Teams working from the same Product Backlog. Several of the developers have come to you complaining that work identified for the upcoming two Sprints will require full-time commitment from a technical specialist who is external to the teams. What are two key concerns for the Scrum Master to take into account in this situation? (Choose two.)
A. The desire to maintain a stable velocity.
B. The benefit of Development Teams figuring out a solution for themselves.
C. The need to have enough work to keep all Development Team members busy.
D. The ability of the Scrum Teams to produce integrated Increments.
Answer
B, D
Q52. You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (Choose two.)
A. There should be six Product Owners, one for each Scrum Team.
B. There should be six Product Owners, reporting to a chief Product Owner.
C. The product has one Product Backlog.
D. Each Scrum Team should have a separate Product Backlog.
E. There should be only one Product Owner.
Answer
D
Q53. A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog.
However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)
A. Ensuring that the most valuable functionality is produced first, at all times.
B. Interacting with stakeholders.
C. Providing the Development Team with detailed specifications.
D. Describing features as Use Cases.
E. Creating detailed functional test cases.
Answer
A, B
Q54. Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose two.)
A. Definition of ג€Doneג€.
B. How the team does its work.
C. Team relations.
D. The value of work currently represented in the Product Backlog.
E. Arranging the Sprint Backlog for the next Sprint.
Answer
D, E
Q55. What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?
A. There are no such activities. The next Sprint starts immediately after the current Sprint.
B. Refine the Product Backlog.
C. Work with the Quality Assurance departments on the Increment of the current Sprint.
D. Update the project plan with stakeholders.
Answer
A
Q56. Which of the following are roles on a Scrum Team? (Choose three.)
A. Users
B. Scrum Master
C. Product Owner
D. Development Team
E. Customers
Answer
B, C, D
Q57. Which best describes the Product Backlog?
A. It is allowed to grow and change as more is learned about the product and its customers.
B. It provides just enough information to enable a Scrum team to start the design phase of a product.
C. It contains all foreseeable tasks and requirements from which the Scrum team can develop and maintain a complete project plan.
D. It is baselined to follow change management processes.
Answer
A
Q58. If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team? (Choose the best answer.)
A. Its productivity is likely to decrease.
B. Its productivity is likely to stay the same.
C. Its productivity is likely to increase.
D. We do not know until a Sprint has run.
Answer
A
Q59. A Scrum Master is introducing Scrum to a new Team. The Team has decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take?
A. Call a meeting between the Scrum Team and senior management.
B. Comply with the decision of the self-organizing team.
C. Consult with the Product Owner to see how they feels about the situation.
D. Begin facilitating productive and useful Sprint Retrospectives.
Answer
D
Q60. Which of the following are true about the Product Owner role? (Choose two.)
A. The Product Owner is one person.
B. The Product Owner is accountable for ordering the Product Backlog.
C. Multiple people can share the Product Owner role on a Scrum Team.
D. The Product Owner role can be played by a committee or a team of people.
Answer
A, B