Q21. What factor should be considered when establishing the Sprint length?
A. The frequency at which team formation can be changed.
B. The organization has mandated similar length sprints.
C. The organization’s release schedule.
D. The need for the team to learn based on doing work and measuring results.
Answer
D
Q22. Who does the work to make sure Product Backlog items conform to the Definition of Done? (Choose the best answer.)
A. The Quality Assurance Team.
B. The Scrum Master.
C. The Developers
D. The Product Owner.
E. The Scrum Team.
Answer
C
Q23. Who creates the Definition of Done? (Choose the best answer.)
A. The Scrum Team
B. The Scrum Master
C. The Product Owner
D. The Developers
Answer
A
Q24. Which two things should the Scrum Team do during the first Sprint? (Choose two.)
A. Make up a plan for the rest of the project.
B. Define the major product features and a release plan architecture.
C. Build at least one piece of valuable functionality.
D. Analyze, describe, and document the requirements for the subsequent Sprints.
E. Create at least one valuable, useful Increment.
Answer
C, E
Q25. When does a Developer become accountable for an item in the Sprint Backlog? (Choose the best answer.)
A. During the Daily Scrum.
B. As soon as a Developer on the Scrum Team can accommodate more work.
C. Never. All Developers on the Scrum Team share accountability for items in the Sprint Backlog.
D. At Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers.
Answer
C
Q26. When does a Sprint conclude? (Choose the best answer.)
A. When all Product Backlog items meet their Definition of Done.
B. When the Sprint Retrospective is complete.
C. When the Product Owner decides enough has been delivered to meet the Sprint Goal.
D. When all the tasks are completed by the Developers.
Answer
B
Q27. What tactic should a Scrum Team use to divide a group of 100 people into multiple Scrum Teams? (Choose the best answer.)
A. Ask the people to divide themselves into teams.
B. Ask the Product Owner to assign the people to teams.
C. Create teams based on their skills across multiple layers (such as database, UI, etc.)
Answer
A
Q28. The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.
A. True
B. False
Answer
A
Q29. When must a Product Owner release each Increment? (Choose the best answer.)
A. When it makes sense to release it.
B. When the Scrum Team finishes their work.
C. Whenever the product is free of defects.
D. After every Sprint, without exception.
Answer
A
Q30. Which of the following is an example of an Increment? (Choose the best answer.)
A. A plan for the overall product release.
B. A mock-up of the product marketing materials.
C. A design for the product.
D. A product roll-out plan.
E. A valuable, useful set of products featured.
F. All of the above.
Answer
E