Q161. True or False: Scrum has a role called `Project Manager`.
A. True
B. False
Answer
B
Q162. What are two effective ways for the Scrum Team to make non-functional requirements visible? (Choose two.)
A. Put them on a separate list on the Scrum board, available for all to see.
B. Add them to the Product Backlog to ensure transparency.
C. Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.
D. Add them to the definition of `Done` so the work is taken care of every Sprint.
Answer
B, D
Q163. How much time is required after a Sprint to prepare for the next Sprint?
A. The break between Sprints is time-boxed to 1 week for 30-day Sprints, and usually less for shorter sprints.
B. Enough time for the requirements for the next Sprint to be determined and documented.
C. Enough time for the Development team to finish the testing from the last Sprint.
D. None. A new Sprint starts immediately following the end of the previous Sprint.
E. All of the above are allowed depending on the situation.
Answer
D
Q164. During Sprint Planning the Product Owner and the Developers are unable to reach an understanding about the highest order Product Backlog items. Because of this, the Developers are unable to determine how many Product Backlog items they can forecast for the upcoming Sprint. However, the Product Owner and the
Developers are able to agree on a Sprint Goal.
Which of the following actions should the Scrum Master support? (Choose two.)
A. Cancel the Sprint. Send the entire team to an advanced Scrum training and then start a new Sprint.
B. Forecast the Product Backlog items that are most likely to meet the Sprint Goal and create the Sprint Backlog. Conclude Sprint Planning and start the development work. Continue to analyze, decompose, and create additional functionality during the Sprint.
C. Continue the Sprint Planning event past its timebox until an adequate number of Product Backlog items are well enough understood for the Developers to make a complete forecast. Then start the Sprint.
D. During the next Sprint Retrospective discuss why this happened and what changes will make it less likely to recur.
E. Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint Planning meeting.
Answer
B, D
Q165. Who can cancel a Sprint?
A. The Scrum Team.
B. The Scrum Master.
C. The Product Owner.
D. The Stakeholders.
Answer
C
Q166. Which of the following is required by Scrum?
A. Sprint Retrospective.
B. Members must stand up at the Daily Scrum.
C. Sprint Burndown Chart.
D. Release planning.
E. All of the above.
Answer
A
Q167. What is the purpose of a Sprint Review?
A. To take time to judge the validity of the project.
B. To inspect the product Increment with the stakeholders and collect feedback on next steps.
C. To review the Scrum Team’s activities and processes during the Sprint.
D. To build team sprint.
Answer
B
Q168. Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
A. The Project Manager.
B. The Development Team.
C. The Scrum Team.
D. The Product Owner.
Answer
B
Q169. Who must attend the Daily Scrum?
A. The Scrum Master and Product Owner.
B. The Development Team.
C. The Development Team and Product Owner.
D. The Scrum Team.
E. The Development Team and Scrum Master.
Answer
B
Q170. When do Development Team members take ownership of a Sprint Backlog item? (Choose the best answer.)
A. At the Sprint planning meeting.
B. During the Daily Scrum.
C. Never. All Sprint Backlog Items are `owned` by the entire Scrum Team.
D. Whenever a team member can accommodate more work.
Answer
C